In 2022, META Engineering AG initiated the implementation of a wind plant project in Lithuania. This wind plant comprises two wind turbines, with an estimated annual electricity production capacity of 27,000 megawatt-hours (MWh).
The project aims to harness the abundant wind resources in Lithuania to generate clean and sustainable energy. By utilizing wind power, META Engineering AG contributes to the reduction of carbon emissions and promotes renewable energy adoption in the region.
The wind power plant is anticipated to reach full operational capacity in early 2025. Upon completion, these turbines will supply significant amounts of clean electricity to the local grid.
Location:
Marijampole district, Lithuania
Technical data:
3 units x 4.2 MW Enercon E-138 wind turbines
Construction period:
Started in 2022
Completed in 2025 January.
Harnessing Lithuania's wind resources to generate sustainable energy, with an annual capacity of 41,000 MWh.
A pioneering 326 MW wind power project contributing over 1,000,000 MWh annually, fostering regional development and clean energy production.
Transitioning to a green petroleum logistics hub in Riga, Latvia, focusing on the sustainable storage and transshipment of biofuels.